Company Schedule Setup

Rosie Arkusinski Updated by Rosie Arkusinski

To enhance the scheduling feature in XactRemodel, customize your schedule settings to ensure that the auto-schedule feature within a project respects your specific company's schedule.

The ability to schedule projects in XactRemodel is available to users on the XactRemodel PRO subscription. To upgrade your subscription to XactRemodel PRO, contact our sales team at 1-833-352-9228.

Work Week Schedule

Within the work week, the user has the ability to specify the hours and days in which events can automatically be scheduled. XactRemodel references this information when it auto-schedules a project to ensure it conforms to your company's schedule.

How to Schedule a Work Week

  1. In the primary navigation menu, go to the Settings page.
  2. Navigate to the Schedule card.
  3. Underneath Work week, click on the time range for the day to be edited.
  4. In the window that appears, indicate that it is a working day by clicking on the slider icon to turn it orange or gray if it is a non-working day.
  5. Enter the start and end time for that day and click Save.

Non-Working Dates

Adding non-working days prevents a task from being scheduled on that day. When the user is auto-generating a project, the project will be scheduled around the non-working dates. These days can include holidays, vacations, and any other planned closures.

How to Schedule Non-Working Dates

  1. In the primary navigation, go to the Settings page.
  2. Navigate to the Schedule card. Underneath Non-working dates, click Add non-working date.
  3. In the window that appears, type the description of the event and select the non-working date by typing it in or selecting it on the calendar provided.
  4. Click Add to add the non-working date to your calendar.
To update the schedule within a project with the latest work week and non-working date changes, navigate to the Schedule tab within a project, select the magic wand icon at the top right, and click Sync. This will update the length of the tasks to account for the schedule settings that were configured. If you want the start dates to all be reset, you can click the magic wand icon and clear the schedule then click the magic wand icon again and click Sync.

How did we do?

Adding Tasks to your Project Schedule

Contact